102
0

Court orders have been issued for the immediate conduct of inquiries with respect to the spending of 79.2 million rupees on a kerosene tank project within the Hambantota Harbour premises.

The Special Investigative Division informed the judiciary that a sum of 79.2 million rupees had been spent on the construction of kerosene tanks at the Hambantota Harbour.

The Unit further informed the Court that investigations were still proceeding. Colombo Fort Magistrate Lanka Jayaratne ordered to expedite the investigations.